During the “6.30” period, there has three PV power station has been grid-connected successfully in Ningxia autonomous region and Zhenjiang city, Jiangsu province. The PV power station where located in Ningxia Autonomous region is named as “Xin ken, Jianquan” with 30 MW capacity. And other two power station were be designed as ‘fishery + solar’ model, which is “Zhenjiang, Xiexin” with 20MW and second phase of “Zhenjiang, Xinlong” with 15MW. As new member of the regional operation and maintenance center in this area, it expands the company’s operation and maintenance capabilities.
“Xinken, Jianquan” PV power station is located in Shizuishan city, Ningxia Autonomous region. This area is part of Shizuishan Intermountain Fault Basin and near with Yinchuan Fault Basin. At the end of 2016, the first Regional operation and maintenance Center has been operated in Zhongwei city, Ningxia Hui Autonomous Region, located on edge of the Tengger Desert. The total operation and maintenance scale of this center has been designed to dozens of GW capacity. This operation and maintenance center also is the first one in China. Before “Xinken, Jianquan” PV power station connected into this operation and maintenance center system, there has already seven PV power plants operation and maintenance by this center. As the eighth PV power station in this area that maintenance by this center, the total capacity of operation and maintenance scale of this center has increase to 360MW.

“Zhenjiang, Xiexin” and second phase of “Zhenjiang, Xinlong” , as the fourth and fifth fishery-solar PV power plant that completed by our company in Zhenjiang county, Suzhou city. After grid-connected successfully, the number of PV power plants in ‘fishery-solar’ model that operated by our company has increased to five and the total capacity has reached 80MW. And GCL New Energy become the largest ‘fishery-solar’ PV power plants developer in Zhenjiang county.

Before this time period, there has three ‘fishery-solar’ PV power station grid-connected in this area, which named as “Zhenjiang, Xinli”, “Jurong, Xinda” and First phase of “Zhenjiang, Xinlong”. These PV power station has operation stable and starts to generate economic benefits for company. “Jurong, Xinda” is a demonstration ‘fishery+solar’ PV power station among these power plants, it combined fish farming and hydroponic vegetable cultivation to create an ecological cycle model.

Because of these five ‘fishery-solar’ PV power stations are not located far apart from each other, and all under controlled by same operation and maintenance center. So the human cost and maintenance cost has been reduced lot by this operation system, and economic benefits also increased in same time. It further demonstrates the company's expertise ability in the development, construction and operation of PV power plants.